Fire Station 3 Replacement

Project Description

Fire Station 3 is located at (US 776) El Jobean Road and Newcomb Road. It was built in 1977 and is at the end of the life cycle of the building. The present building is undersized and does not meet the current and future needs including,

  • not hardened for hurricane resistance
  • lack of capacity for storage, equipment, apparatus and supplies.
  • inadequate personnel capacity and kitchen facilities.

Project Impacts

Weather

ACOE (Army Corps of Engineers)

Latest Updates

Charlotte County Fire & EMS is currently contracted with a professional consultant to perform a countywide evaluation of call response times. This evaluation will help determine the location of this station as well as future fire station locations.

Budget

Phase Cost
Design $200,000.00
Construction $4,334,000.00
Other Costs $300,000.00
Total Budget $4,834,000.00
Funding source(s): 2020 Sales Tax

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 11/16/2023 02/27/2024
Design Development 03/01/2024 02/01/2025
Construction 02/01/2024 02/01/2025
Turnover & Closeout 03/01/2025 04/01/2025

Project Phase
Planning and Project Approval

Last Updated
11/22/2024

Project Manager
Joe Romanelli

Public Relations
Todd Dunn
Email Public Relations

Project Number
c222103

Sponsor Department
Public Safety Charlotte County Fire and EMS

Design Engineer/Architect
Schenkel Shultz

Construction Contractor
Wharton-Smith/Jon F. Swift

Sales Tax Project